Greene County 2
10 MW generation in Greene, NY · In queue since September 2016 · Proposed COD May 2025
10 MW
Capacity
1
Components
Solar
9y 6m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
8y 8m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-05-01
State
NY
County
Greene
Region
NYISO
Developer
Hecate Energy Greene 2 LLC
Utility
CHG&E
Entity
NYISO
Point of Interconnection
Coxsackie 13.8kV
Data Source
LBNL
Hecate Energy Sells Up To 2,000 MW Cereza Solar-Plus-Storage Project At DOE’s Hanford Site To Savion, Marking Major Milestone In Large-Scale Energy Campus Strategy
Hecate Energy Transfers 2 GW Hanford Site Cereza Project to Savion as Company Exceeds 12 GW in Projects Sold and Expands Revenue Backlog.
Greenbacker secures nearly $1 billion financing to support
Greenbacker, together with Hecate Energy, has completed the development of its largest clean energy project to date.
Flatiron Energy gets ISO green light for 1.2GWh indoor BESS in Boston, Massachusetts
System operator ISO New England has given the green light for a large, indoor BESS in Boston, Massachusetts, from developer Flatiron Energy.
Last updated 2026-03-26