Sky High Solar
BetaActiveSolarNYISOLBNL
20 MW generation in Onondaga, NY · In queue since May 2016 · Proposed COD June 2025
20 MW
Capacity
1
Components
Solar
9y 10m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
9y 1m
Schedule
10 months past proposed COD
Facilities Study50%
Queue EntryMay 16, 2016
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
NY
County
Onondaga
Region
NYISO
Developer
Sky High Solar, LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Tilden -Tully Center 115kV
Data Source
LBNL
No news available for this project.