Riverhead Solar 2 — Project Summary

Queue ID
NYISO-535
Capacity
36 MW
Technology
Solar
Status
active
Location
Suffolk, NY
Region
NYISO
Developer
Riverhead Solar 2, LLC
IA Status
Facility Study

Riverhead Solar 2

BetaActiveSolarNYISOLBNL

36 MW generation in Suffolk, NY · In queue since February 2016 · Proposed COD January 2027

36 MW

Capacity

1

Components

Solar

10y 1m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

10y 11m

Facilities Study50%
Queue EntryFeb 23, 2016

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-01-01

Project Details

State

NY

County

Suffolk

Region

NYISO

Developer

Riverhead Solar 2, LLC

Utility

LIPA

Entity

NYISO

Point of Interconnection

Edwards 138kV

Data Source

LBNL