Bull Run II Wind
BetaActiveWindNYISOLBNL
449 MW generation in Clinton, NY · In queue since December 2015 · Proposed COD December 2026
449 MW
Capacity
1
Components
Wind
10y 3m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
11 years
Facilities Study50%
Queue EntryDec 15, 2015
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
NY
County
Clinton
Region
NYISO
Developer
Bull Run Energy LLC
Utility
NYPA
Entity
NYISO
Point of Interconnection
Patnode-Duley, Ryan-Plattsburgh 230kV
Data Source
LBNL
No news available for this project.