Canisteo Wind — Project Summary

Queue ID
NYISO-519
Capacity
289.8 MW
Technology
Wind
Status
active
Location
Steuben, NY
Region
NYISO
Developer
Canisteo Wind Energy LLC
IA Status
Facility Study

Canisteo Wind

BetaActiveWindNYISOLBNL

289.8 MW generation in Steuben, NY · In queue since November 2015 · Proposed COD December 2027

289.8 MW

Capacity

1

Components

Wind

10y 4m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

12y 1m

Facilities Study50%
Queue EntryNov 2, 2015

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Project Details

State

NY

County

Steuben

Region

NYISO

Developer

Canisteo Wind Energy LLC

Utility

NYSEG

Entity

NYISO

Point of Interconnection

Bennett 115kV

Data Source

LBNL