Mohawk Solar
BetaActiveSolarNYISOLBNL
90.5 MW generation in Montgomery, NY · In queue since April 2015 · Proposed COD November 2027
90.5 MW
Capacity
1
Components
Solar
10y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
12y 7m
Facilities Study50%
Queue EntryApr 2, 2015
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-11-01
Project Details
State
NY
County
Montgomery
Region
NYISO
Developer
Mohawk Solar LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
St. Johnsville - Marshville 115kV
Data Source
LBNL