Homer Solar Energy Center
BetaActiveSolarNYISOLBNL
90 MW generation in Cortland, NY · In queue since January 2008 · Proposed COD April 2026
90 MW
Capacity
1
Components
Solar
18y 2m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
18y 3m
Facilities Study50%
Queue EntryJan 30, 2008
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-04-01
Project Details
State
NY
County
Cortland
Region
NYISO
Developer
Homer Solar Energy Center LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Cortland - Fenner 115kV
Data Source
LBNL
No news available for this project.