Site Master Plan Expansion Phase I
BetaActiveLNYISOLive · NYISO
45 MW generation in Albany, NY · In queue since December 2025
45 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
3 months
Pre-Study0%
Queue EntryDec 18, 2025
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NY
County
Albany
Region
NYISO
Developer
Research Foundation of SUNY
Utility
National Grid
Entity
NYISO
Point of Interconnection
Patroon Creek and McKnownville
Data Source
Live · NYISO