New York State Dept. of Health Lab (Harriman Campus, Albany NY)
BetaActiveLNYISOLive · NYISO
20 MW generation in Albany, NY · In queue since November 2025
20 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
4 months
Pre-Study0%
Queue EntryNov 4, 2025
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NY
County
Albany
Region
NYISO
Developer
New York State Office of General Services
Utility
National Grid
Entity
NYISO
Point of Interconnection
Woodlawn-State Campus #12 115kV feeder, and Menands-State Campus #15-115kV feeder.
Data Source
Live · NYISO