Broome County Tech Park
BetaActiveLNYISOLive · NYISO
250 MW generation in Broome, NY · In queue since October 2025
250 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
5 months
Pre-Study0%
Queue EntryOct 30, 2025
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NY
County
Broome
Region
NYISO
Developer
The Agency
Utility
NYSEG
Entity
NYISO
Point of Interconnection
345 kV POI via a loop on the existing Oakdale-Fraser Line 32. The interconnection substation will have a ring bus configuration.
Data Source
Live · NYISO