Al Tech Steel Site
BetaActiveLNYISOLive · NYISO
60 MW generation in Albany, NY · In queue since October 2025
60 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
5 months
Pre-Study0%
Queue EntryOct 21, 2025
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NY
County
Albany
Region
NYISO
Developer
Advance Albany County Alliance
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Maplewood Menands 18
Data Source
Live · NYISO
No news available for this project.