Globe DH 3
BetaActiveLNYISOLive · NYISO
100 MW generation in niagara falls, NY · In queue since October 2025
100 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
5 months
Pre-Study0%
Queue EntryOct 17, 2025
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NY
County
niagara falls
Region
NYISO
Developer
GLOBE DH LLC
Utility
National Grid
Entity
NYISO
Point of Interconnection
lines 187 and 188
Data Source
Live · NYISO
No news available for this project.