OOWWTP Expansion Program
BetaActiveLNYISOLive · NYISO
50 MW generation in Onondaga, NY · In queue since October 2025
50 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
5 months
Pre-Study0%
Queue EntryOct 15, 2025
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NY
County
Onondaga
Region
NYISO
Developer
Onondaga County Department of Water Environment Protection
Utility
National Grid
Entity
NYISO
Point of Interconnection
National Grid's 115kV lines: Clay-Teall LN#11 and Clay-Woodard LN#17
Data Source
Live · NYISO
No news available for this project.