St. Lawrence Infrastructure 2
BetaActiveLNYISOLive · NYISO
1,935 MW generation in St. Lawrence, NY · In queue since September 2025
1,935 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
6 months
Pre-Study0%
Queue EntrySep 2, 2025
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NY
County
St. Lawrence
Region
NYISO
Developer
St. Lawrence Infrastructure, LLC
Utility
NYPA
Entity
NYISO
Point of Interconnection
NYPA's 230kV Moses Massena 1 (MMS-1) and 230kV Moses Massena 2 (MMS-2)
Data Source
Live · NYISO