Cayuga Data
BetaActiveLNYISOLive · NYISO
162 MW generation in Tompkins, NY · In queue since March 2025
162 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Interconnection Timeline
Total Duration
1 year
Pre-Study0%
Queue EntryMar 29, 2025
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NY
County
Tompkins
Region
NYISO
Developer
Cayuga Operating Company, LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Milliken 115kV Substation
Data Source
Live · NYISO