Wulf Compute Data Center II
BetaActiveLNYISOLive · NYISO
250 MW generation in Niagara, NY · In queue since March 2025
250 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Interconnection Timeline
Total Duration
1 year
Pre-Study0%
Queue EntryMar 29, 2025
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NY
County
Niagara
Region
NYISO
Developer
TeraWulf Brookings LLC
Utility
NYSEG
Entity
NYISO
Point of Interconnection
Kintigh 345kV sub-station
Data Source
Live · NYISO
No news available for this project.