Data & Technology Campus
BetaActiveLNYISOLive · NYISO
300 MW generation in Erie, NY · In queue since January 2025
300 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Interconnection Timeline
Total Duration
1y 2m
Pre-Study0%
Queue EntryJan 31, 2025
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NY
County
Erie
Region
NYISO
Developer
Riverview Innovation & Technology Campus, Inc.
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Huntley - Packard 230kV line 78
Data Source
Live · NYISO
No news available for this project.