Edwards Calverton Battery Storage — Project Summary

Queue ID
NYISO-1257
Capacity
60 MW
Technology
Battery
Status
active
Location
Suffolk, NY
Region
NYISO
Developer
Edwards Calverton Battery Storage
IA Status
System Impact Study

Edwards Calverton Battery Storage

BetaActiveBatteryNYISOLBNL + Live

60 MW storage in Suffolk, NY · In queue since September 2021 · Proposed COD March 2025

60 MW

Capacity

1

Components

Battery

4y 6m

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 6m

Schedule

13 months past proposed COD

Impact Study25%
Queue EntrySep 22, 2021

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-03-01

Project Details

State

NY

County

Suffolk

Region

NYISO

Developer

Edwards Calverton Battery Storage

Utility

LIPA

Entity

NYISO

Point of Interconnection

Edwards Avenue Substation at 138 kV

Data Source

LBNL + Live