NY125A - Fort Covington Solar
BetaActiveSolarNYISOLBNL + Live
250 MW generation in Franklin, NY · In queue since May 2021 · Proposed COD August 2027
250 MW
Capacity
1
Components
Solar
4y 10m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 3m
Impact Study25%
Queue EntryMay 20, 2021
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-08-01
Project Details
State
NY
County
Franklin
Region
NYISO
Developer
Fort Covington Solar LLC
Utility
NYPA
Entity
NYISO
Point of Interconnection
Moses-Willis 230 kV (MW1)
Data Source
LBNL + Live
No news available for this project.