York Run Solar — Project Summary

Queue ID
NYISO-1151
Capacity
90 MW
Technology
Solar
Status
active
Location
Chautauqua, NY
Region
NYISO
Developer
York Run Solar, LLC
IA Status
System Impact Study

York Run Solar

BetaActiveSolarNYISOLBNL + Live

90 MW generation in Chautauqua, NY · In queue since March 2021 · Proposed COD August 2026

90 MW

Capacity

1

Components

Solar

5 years

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

5y 5m

Impact Study25%
Queue EntryMar 18, 2021

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-08-01

Project Details

State

NY

County

Chautauqua

Region

NYISO

Developer

York Run Solar, LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Falconer - Warren 115 kV line #171

Data Source

LBNL + Live

No news available for this project.