Hoffman Falls Wind
72 MW generation in Madison, NY · In queue since January 2021 · Proposed COD December 2027
72 MW
Capacity
1
Components
Wind
5y 2m
In Queue
—
IA Status
COD target: 2027
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
State
NY
County
Madison
Region
NYISO
Developer
Liberty Renewables Inc.
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Cortland - Fenner 115kV Line #3
Data Source
LBNL + Live
Fenner has been proud home of wind power but greets new renewable plans skeptically
The Fenner Wind Farm was groundbreaking when built in 2001, and has educated about renewable energy since. A new wind power and a solar...
‘A true betrayal’: Madison County residents, officials oppose wind project
TOWN OF FENNER, N.Y. — Controversy is continuing over a proposed windmill farm in the town of Fenner. It's a standoff between a renewable...
‘A true betrayal’: Madison County residents, officials oppose wind project
TOWN OF FENNER, N.Y. — Controversy is continuing over a proposed windmill farm in the town of Fenner. It's a standoff between a renewable...
Madison County officials say new wind farm could impact public safety
WAMPSVILLE — Madison County officials are raising concerns that a proposed wind farm could interfere with emergency communications.
Last updated 2026-03-26