KCE NY 29
BetaActiveBatteryNYISOLBNL + Live
150 MW storage in Suffolk, NY · In queue since December 2020 · Proposed COD October 2027
150 MW
Capacity
1
Components
Battery
5y 3m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 10m
Pre-Study0%
Queue EntryDec 14, 2020
Interconnection request submitted to ISO/RTO
TCS Study
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-01
Project Details
State
NY
County
Suffolk
Region
NYISO
Developer
KCE NY 29, LLC
Utility
LIPA
Entity
NYISO
Point of Interconnection
Kings 138 kV
Data Source
LBNL + Live
No news available for this project.