East Fishkill
BetaActiveBatteryNYISOLBNL + Live
205 MW storage in Dutchess, NY · In queue since December 2020 · Proposed COD November 2028
205 MW
Capacity
1
Components
Battery
5y 3m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 11m
Impact Study25%
Queue EntryDec 11, 2020
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-11-01
Project Details
State
NY
County
Dutchess
Region
NYISO
Developer
Microgrid Networks, LLC
Utility
CHG&E
Entity
NYISO
Point of Interconnection
Shenandoah 115kV
Data Source
LBNL + Live
No news available for this project.