Flat Creek Solar 2
BetaActiveSolarNYISOLBNL + Live
100 MW generation in Montgomery, NY · In queue since November 2020 · Proposed COD November 2028
100 MW
Capacity
1
Components
Solar
5y 4m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8 years
Impact Study25%
Queue EntryNov 23, 2020
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-11-01
Project Details
State
NY
County
Montgomery
Region
NYISO
Developer
SED NY Holdings LLC
Utility
NYPA
Entity
NYISO
Point of Interconnection
Edic - Princetown 345 kV Line# 352
Data Source
LBNL + Live