Flat Creek Solar
BetaActiveSolarNYISOLBNL + Live
200 MW generation in Montgomery, NY · In queue since September 2020 · Proposed COD November 2028
200 MW
Capacity
1
Components
Solar
5y 6m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 2m
Impact Study25%
Queue EntrySep 4, 2020
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-11-01
Project Details
State
NY
County
Montgomery
Region
NYISO
Developer
SED NY Holding LLC
Utility
NYPA
Entity
NYISO
Point of Interconnection
Edic to Princetown 345kV Line 352
Data Source
LBNL + Live
No news available for this project.