Flat Creek Solar — Project Summary

Queue ID
NYISO-1089
Capacity
200 MW
Technology
Solar
Status
active
Location
Montgomery, NY
Region
NYISO
Developer
SED NY Holding LLC
IA Status
System Impact Study

Flat Creek Solar

BetaActiveSolarNYISOLBNL + Live

200 MW generation in Montgomery, NY · In queue since September 2020 · Proposed COD November 2028

200 MW

Capacity

1

Components

Solar

5y 6m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

8y 2m

Impact Study25%
Queue EntrySep 4, 2020

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-01

Project Details

State

NY

County

Montgomery

Region

NYISO

Developer

SED NY Holding LLC

Utility

NYPA

Entity

NYISO

Point of Interconnection

Edic to Princetown 345kV Line 352

Data Source

LBNL + Live

No news available for this project.