Somerset Solar — Project Summary

Queue ID
NYISO-1079
Capacity
125 MW
Technology
Solar
Status
active
Location
Niagara, NY
Region
NYISO
Developer
Somerset Solar, LLC
IA Status
System Impact Study

Somerset Solar

BetaActiveSolarNYISOLBNL + Live

125 MW generation in Niagara, NY · In queue since August 2020 · Proposed COD March 2027

125 MW

Capacity

1

Components

Solar

5y 7m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

6y 7m

Impact Study25%
Queue EntryAug 18, 2020

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-01

Project Details

State

NY

County

Niagara

Region

NYISO

Developer

Somerset Solar, LLC

Utility

NYSEG

Entity

NYISO

Point of Interconnection

Kintigh 345 kV