Morris Solar — Project Summary

Queue ID
NYISO-1039
Capacity
20 MW
Technology
Solar
Status
active
Location
St. Lawrence, NY
Region
NYISO
Developer
SED NY Holdings LLC
IA Status
Facility Study

Morris Solar

BetaActiveSolarNYISOLBNL + Live

20 MW generation in St. Lawrence, NY · In queue since January 2021 · Proposed COD December 2025

20 MW

Capacity

1

Components

Solar

5y 2m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 11m

Schedule

4 months past proposed COD

Facilities Study50%
Queue EntryJan 6, 2021

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-01

Project Details

State

NY

County

St. Lawrence

Region

NYISO

Developer

SED NY Holdings LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Battle Hill - Balmat 115kV

Data Source

LBNL + Live