Yellow Barn Solar — Project Summary

Queue ID
NYISO-1009
Capacity
160 MW
Technology
Solar
Status
active
Location
Tompkins, NY
Region
NYISO
Developer
Yellow Barn Solar, LLC
IA Status
System Impact Study

Yellow Barn Solar

BetaActiveSolarNYISOLBNL + Live

160 MW generation in Tompkins, NY · In queue since April 2020 · Proposed COD December 2025

160 MW

Capacity

1

Components

Solar

5y 11m

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

5y 8m

Schedule

4 months past proposed COD

Impact Study25%
Queue EntryApr 30, 2020

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-01

Project Details

State

NY

County

Tompkins

Region

NYISO

Developer

Yellow Barn Solar, LLC

Utility

NYSEG

Entity

NYISO

Point of Interconnection

Milliken - Etna 115 kV line #975