NYC Energy LLC - Phase 2
BetaActiveBatteryNYISOLBNL + Live
220.1 MW storage in Kings, NY · In queue since April 2020 · Proposed COD June 2027
220.1 MW
Capacity
1
Components
Battery
5y 11m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 2m
Impact Study25%
Queue EntryApr 22, 2020
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
NY
County
Kings
Region
NYISO
Developer
NYC Energy
Utility
ConEd
Entity
NYISO
Point of Interconnection
Hudson Ave 138 kV
Data Source
LBNL + Live