SunEast Flat Stone Solar LLC — Project Summary

Queue ID
NYISO-1000
Capacity
20 MW
Technology
Solar
Status
active
Location
Oneida, NY
Region
NYISO
Developer
SED NY Holdings LLC
IA Status
Facility Study

SunEast Flat Stone Solar LLC

BetaActiveSolarNYISOLBNL + Live

20 MW generation in Oneida, NY · In queue since March 2020 · Proposed COD November 2026

20 MW

Capacity

1

Components

Solar

6 years

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

6y 8m

Facilities Study50%
Queue EntryMar 18, 2020

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-11-01

Project Details

State

NY

County

Oneida

Region

NYISO

Developer

SED NY Holdings LLC

Utility

NM-NG

Entity

NYISO

Point of Interconnection

Oneida - Rome 115kV

Data Source

LBNL + Live