Hills Solar
20 MW generation in Herkimer, NY · In queue since November 2025
20 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
Total Duration
4 months
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
State
NY
County
Herkimer
Region
NYISO
Developer
SunEast Hills Solar LLC
Utility
NM-NG
Entity
NYISO
Point of Interconnection
Fairfield - Inghams 115kV
Data Source
Live · NYISO
DESRI and Cleco Power Announce Start of Construction at Dolet Hills Solar Facility in DeSoto Parish
DESRI, in partnership with Cleco Power, today announced that construction has begun on the 240-megawatt (MWac) Dolet Hills Solar Project...
powering the world forward with california sunshine
The Lost Hills Solar Project, a 29-megawatt AC system of solar panels, began delivering low-carbon electricity to Chevron's Lost Hills oil field in Kern County...
Cleco Power and DESRI Announce 240 MWac Solar Power Agreement
The Dolet Hills Solar Project includes a 240 MWac facility to be constructed at the recently retired Dolet Hills lignite-fired power plant in DeSoto Parish,...
Cleco Power and DESRI Announce 240 MWac Solar Power Agreement
The Dolet Hills Solar Project includes a 240 MWac facility to be constructed at the recently retired Dolet Hills lignite-fired power plant in DeSoto Parish,...