150 MW generation in Broadwater, MT · In queue since June 2024 · Proposed COD December 2029
150 MW
Capacity
1
Components
Gas
1y 9m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 6m
Pre-Study0%
Queue EntryJun 7, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-31
Project Details
State
MT
County
Broadwater
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
Three Rivers Substation
Data Source
LBNL
No news available for this project.