— Project Summary

Queue ID
NWMT-463
Capacity
0.5 MW
Technology
Gas
Status
active
Location
Beadle, SD
Region
West
Developer
IA Status

BetaActiveGasNWMTLBNL

0.5 MW generation in Beadle, SD · In queue since June 2024 · Proposed COD March 2025

0.5 MW

Capacity

1

Components

Gas

1y 9m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

9 months

Schedule

12 months past proposed COD

Pre-Study0%
Queue EntryJun 5, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-03-31

Project Details

State

SD

County

Beadle

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

Huron Substation

Data Source

LBNL

No news available for this project.