BetaActiveGasNWMTLBNL
0.5 MW generation in Beadle, SD · In queue since June 2024 · Proposed COD March 2025
0.5 MW
Capacity
1
Components
Gas
1y 9m
In Queue
—
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
9 months
Schedule
12 months past proposed COD
Pre-Study0%
Queue EntryJun 5, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-03-31
Project Details
State
SD
County
Beadle
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
Huron Substation
Data Source
LBNL
No news available for this project.