— Project Summary

Queue ID
NWMT-457
Capacity
2.2 MW
Technology
Hydro
Status
active
Location
Lewis And Clark, MT
Region
West
Developer
IA Status
System Impact Study

BetaActiveHydroNWMTLBNL

2.2 MW generation in Lewis And Clark, MT · In queue since March 2024 · Proposed COD June 2025

2.2 MW

Capacity

1

Components

Hydro

2 years

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

1y 3m

Schedule

10 months past proposed COD

Impact Study25%
Queue EntryMar 13, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-01

Project Details

State

MT

County

Lewis And Clark

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

Hauser Dam Substation

Data Source

LBNL

No news available for this project.