BetaActiveHydroNWMTLBNL
2.2 MW generation in Lewis And Clark, MT · In queue since March 2024 · Proposed COD June 2025
2.2 MW
Capacity
1
Components
Hydro
2 years
In Queue
System Impact Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
1y 3m
Schedule
10 months past proposed COD
Impact Study25%
Queue EntryMar 13, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
MT
County
Lewis And Clark
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
Hauser Dam Substation
Data Source
LBNL
No news available for this project.