— Project Summary

Queue ID
NWMT-456
Capacity
5 MW
Technology
Gas
Status
active
Location
Brown, SD
Region
West
Developer
IA Status

BetaActiveGasNWMTLBNL

5 MW generation in Brown, SD · In queue since February 2024 · Proposed COD January 2025

5 MW

Capacity

1

Components

Gas

2y 1m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

11 months

Schedule

14 months past proposed COD

Pre-Study0%
Queue EntryFeb 2, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-01-31

Project Details

State

SD

County

Brown

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

Aberdeen Siebrecht substation

Data Source

LBNL

No news available for this project.