BetaActiveSolarNWMTLBNL
2 MW generation in Gallatin, MT · In queue since December 2023 · Proposed COD December 2024
2 MW
Capacity
1
Components
Solar
2y 3m
In Queue
Feasibility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1 year
Schedule
15 months past proposed COD
Feasibility Study13%
Queue EntryDec 11, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
MT
County
Gallatin
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
Three Forks, MT
Data Source
LBNL
No news available for this project.