12 MW generation in Lewis And Clark, MT · In queue since January 2023 · Proposed COD December 2023
12 MW
Capacity
1
Components
Gas
3y 2m
In Queue
System Impact Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
11 months
Schedule
27 months past proposed COD
Impact Study25%
Queue EntryJan 25, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
MT
County
Lewis And Clark
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
Helena Airport
Data Source
LBNL
No news available for this project.