BetaSuspendedWindNWMTLBNL
250 MW generation in Stillwater, MT · In queue since January 2023 · Proposed COD December 2026
250 MW
Capacity
1
Components
Wind
3y 2m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 11m
Suspended50%
Queue EntryJan 5, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
MT
County
Stillwater
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
Columbus-Rapelje 230kV auto substation.
Data Source
LBNL