BetaActiveHydroNWMTLBNL
70 MW generation in Cascade, MT · In queue since December 2022
70 MW
Capacity
1
Components
Hydro
3y 3m
In Queue
Feasibility Study
IA Status
Interconnection Timeline
Total Duration
3y 3m
Feasibility Study13%
Queue EntryDec 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
MT
County
Cascade
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
Crooked Falls Sunstation
Data Source
LBNL
No news available for this project.