— Project Summary

Queue ID
NWMT-435
Capacity
800 MW
Technology
Solar+Battery
Status
active
Location
Rosebud, MT
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBatteryNWMTLBNL

800 MW hybrid in Rosebud, MT · In queue since November 2022 · Proposed COD December 2025

800 MW

Capacity

1

Components

Solar

3y 4m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 1m

Schedule

4 months past proposed COD

Facilities Study50%
Queue EntryNov 4, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-01

Project Details

State

MT

County

Rosebud

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

Colstrip 500kV Substation

Data Source

LBNL