— Project Summary

Queue ID
NWMT-434
Capacity
65 MW
Technology
Solar+Battery
Status
active
Location
Stillwater, MT
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBatteryNWMTLBNL

65 MW hybrid in Stillwater, MT · In queue since September 2022 · Proposed COD November 2025

65 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 2m

Schedule

5 months past proposed COD

Facilities Study50%
Queue EntrySep 6, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-11-01

Project Details

State

MT

County

Stillwater

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

Columbus Rapelje Substation

Data Source

LBNL