200 MW hybrid in Stillwater, MT · In queue since February 2022 · Proposed COD December 2025
200 MW
Capacity
1
Components
Solar
4y 1m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 10m
Schedule
4 months past proposed COD
Facilities Study50%
Queue EntryFeb 11, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
MT
County
Stillwater
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
230 kV line between Columbus-Rapelje and Stillwater Wind
Data Source
LBNL