300 MW generation in Big Horn, MT · In queue since February 2022 · Proposed COD January 2025
300 MW
Capacity
1
Components
Solar
4y 1m
In Queue
System Impact Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 11m
Schedule
15 months past proposed COD
Impact Study25%
Queue EntryFeb 10, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-01
Project Details
State
MT
County
Big Horn
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
230kV line between Huntley and Crossover Substations