750 MW generation in Wheatland, MT · In queue since January 2022 · Proposed COD October 2026
750 MW
Capacity
1
Components
Wind
4y 2m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 9m
Impact Study25%
Queue EntryJan 10, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-10-31
Project Details
State
MT
County
Wheatland
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
New proposed 500kV Substation between Broadview and Townsend
Data Source
LBNL
No news available for this project.