BetaActiveSolarBatteryNWMTLBNL
50 MW hybrid in Wheatland, MT · In queue since November 2021 · Proposed COD December 2022
50 MW
Capacity
1
Components
Solar
4y 4m
In Queue
Facility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 1m
Schedule
39 months past proposed COD
Facilities Study50%
Queue EntryNov 19, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-31
Project Details
State
MT
County
Wheatland
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
230 kV line between Harlowton and Judith Gap
Data Source
LBNL
No news available for this project.