BetaActiveSolarBatteryNWMTLBNL
160 MW hybrid in Broadwater, MT · In queue since September 2021 · Proposed COD December 2023
160 MW
Capacity
1
Components
Solar
4y 6m
In Queue
Facility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 3m
Schedule
28 months past proposed COD
Facilities Study50%
Queue EntrySep 24, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-01
Project Details
State
MT
County
Broadwater
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
Three Rivers 230kV Substation
Data Source
LBNL
No news available for this project.