BetaSuspendedSolarBatteryNWMTLBNL
80 MW hybrid in Gallatin, MT · In queue since June 2021
80 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Facility Study
IA Status
Interconnection Timeline
Total Duration
4y 9m
Suspended50%
Queue EntryJun 1, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
MT
County
Gallatin
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
Three Rivers 161kV Substation
Data Source
LBNL
No news available for this project.