BetaActiveWindNWMTLBNL
326.25 MW generation in Wheatland, MT · In queue since February 2021 · Proposed COD December 2024
326.25 MW
Capacity
1
Components
Wind
5y 1m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 10m
Schedule
15 months past proposed COD
Facilities Study50%
Queue EntryFeb 4, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
MT
County
Wheatland
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
New proposed 500kV Substation between Broadview and Townsend
Data Source
LBNL
No news available for this project.