— Project Summary

Queue ID
NWMT-401
Capacity
70 MW
Technology
Wind
Status
active
Location
Musselshell, MT
Region
West
Developer
IA Status
Facility Study

BetaActiveWindNWMTLBNL

70 MW generation in Musselshell, MT · In queue since January 2021 · Proposed COD November 2023

70 MW

Capacity

1

Components

Wind

5y 2m

In Queue

Facility Study

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 10m

Schedule

29 months past proposed COD

Facilities Study50%
Queue EntryJan 15, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-11-15

Project Details

State

MT

County

Musselshell

Region

West

Developer

Utility

NorthWestern Energy

Entity

NWMT

Point of Interconnection

100kV Roundup Substation

Data Source

LBNL

No news available for this project.