BetaActiveWindNWMTLBNL
70 MW generation in Musselshell, MT · In queue since January 2021 · Proposed COD November 2023
70 MW
Capacity
1
Components
Wind
5y 2m
In Queue
Facility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 10m
Schedule
29 months past proposed COD
Facilities Study50%
Queue EntryJan 15, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-11-15
Project Details
State
MT
County
Musselshell
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
100kV Roundup Substation
Data Source
LBNL
No news available for this project.