BetaActiveWindNWMTLBNL
750 MW generation in — · In queue since August 2020 · Proposed COD October 2023
750 MW
Capacity
1
Components
Wind
5y 7m
In Queue
Facility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 2m
Schedule
29 months past proposed COD
Facilities Study50%
Queue EntryAug 26, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-10-31
Project Details
State
—
County
—
Region
West
Developer
—
Utility
NorthWestern Energy
Entity
NWMT
Point of Interconnection
New proposed 500kV Substation between Broadview and Townsend
Data Source
LBNL
No news available for this project.